The scaffolding should be built like this
Scaffolding is an indispensable important facility in building construction. It is a working platform and work channel built to ensure the safety of high-altitude operations and smooth construction.
In recent years, scaffolding accidents have occurred frequently throughout the country. The basic reason is: the construction plan (work instruction) has dealt with the problem, the construction personnel violated the construction, and the inspection, acceptance and listing were not in place. At present, scaffolding problems in construction sites of construction projects in various places are still everywhere, and potential safety hazards are imminent. Managers must pay enough attention to the safety management of scaffolding. “Strict inspection and acceptance” is particularly important.
When will the scaffolding acceptance be done?
Scaffolding should be accepted in the following stages:
1) After the foundation is completed, before the frame is erected.
2) After the first step of large and medium-sized scaffolding is completed, the erection of the large crossbar is completed.
3) After each erection of 6-8m height.
4) Before applying load on the working surface.
5) After reaching the design height (the scaffolding for each layer of structure construction shall be checked and accepted once).
6) After the freezing area is thawed in the event of winds of grade 6 or above or heavy rain.
7) Deactivate for more than one month.
8) Before removal.